If preble had purchased 180,000 pounds of materials at $7.20 per pound and used 155,000 pounds in production, what would be the materials quantity variance for march?

Respuesta :

Material quantity variance = (Actual quantity - Standard quantity) * Standard price
= (180,000 - 155,000) * $7.20
= $180,000 favorable