While preparing your risk responses, you identify additional risks. What should you do? Add reserves to the project to accommodate the new risks and notify management. Document the risk and calculate the expected monetary value based on the probability and impact of the occurrences. Determine the risk events and the associated costs, then add the cost to the project budget as a reserve. Add 10 percent contingency to the project budget and notify the customer