The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

What is 10.09 to the nearest hundredth
If you exert a force on an object in motion you will change its what?
You have diving lessons every fifth day and swimming lessons every third day.today you have both lessons. In how many days will you have both lessons on the sam
Which uses the correct verbs for formal speech or writing?a. Madelaine liked to dream about what her life would be like if she was Oprah Winfrey.b. Madelaine li
A ball is dropped from the top of a 84-m-high building. What speed does the ball have in falling 3.6s?
millie has a box of 1 hundred cubes. she also has a bag of 70 cubes. how many trains of 10 cubes can she make?
what is the term for figures used to measures economic performance?
43 - w = 8 what does w equal. how?
Carly spends $5 for n notebooks.Write an algebraic expression represent the cost of one notebook
What four concepts are discussed in the political writings of John Milton?